Footings Concrete Calculator — 3 m Footings

Project Details

Choose your project type and enter the dimensions.

metres
mm
mm

Ready-mix bags needed

38

× 20kg bags (including 10% waste)

Volume

0.304 m³

With Waste

0.334 m³

Or Mix Your Own (C20 Mix — 1:2:4)

Cement

108 kg

Sharp Sand

230 kg

Aggregate (20mm)

430 kg

How Much Concrete for Footings?

Strip footings are the standard foundation for garden walls, boundary walls, and low retaining walls in the UK. As a rule of thumb, footings for a garden wall should be at least 225mm thick and sit on firm ground below the topsoil. For 3m of footings (450mm wide x 225mm deep), you may need approximately 0.304m³ of concrete, which is around 38 x 20kg bags of ready-mix. This guide takes you through trench excavation, levelling, and pouring footings that follow good practice. Taller, structural, or retaining walls may need an engineer's design and building control approval.

Planning and Preparation

Dig the trench to the required depth using a mini excavator for long runs or a spade for shorter sections. The trench bottom must be on firm, undisturbed ground — never pour footings onto loose backfill. Standard strip footings for a garden wall should be at least 450mm wide (three times the wall width for a single-skin wall) and 225mm deep minimum. Check the trench is level along its length using a spirit level and straight edge. If the ground slopes, you can step the footings in increments equal to the brick or block course height (typically 225mm). Remove any loose soil from the trench bottom before pouring.

Mixing Concrete

For this project our estimate suggests around 0.304m³ of concrete. You have two options: use approximately 38 x 20kg bags of ready-mixed concrete from a DIY store or builders' merchant, or mix your own using a C20 mix ratio of 1:2:4 by volume. To mix your own, you'll likely need around 107.4kg of Portland cement (5 x 25kg bags), 229.1kg of sharp sand, and 429.6kg of 20mm gravel aggregate — a total of roughly 766kg of materials. For small batches, mix by hand on a clean board or in a wheelbarrow: combine the dry materials first until the colour is uniform, then gradually add water until the mix holds its shape when squeezed but is still workable. For larger volumes, hire a cement mixer — a half-bag (electric) mixer handles most DIY jobs and costs around £25-35 per day from tool hire shops. Avoid adding too much water, as this weakens the finished concrete significantly.

Pouring Technique

Pour the concrete directly into the trench in one continuous operation if possible. The concrete should fill the trench to the marked level on the profile boards. Use a shovel or a piece of timber to work the concrete into the corners and against the trench walls. Tamp the surface level with a straight edge or a length of timber. The top of the footing does not need to be perfectly smooth, but it must be level so that the first course of bricks or blocks sits evenly. If the trench is deep, pour the concrete in layers of about 150mm, compacting each layer before adding the next. For stepped footings on a sloping site, pour the lowest step first, then work uphill, allowing each section to support the next.

Weather Considerations

Footings are typically poured into a trench, which offers some natural protection from wind and direct sun. However, the same temperature rules apply: avoid pouring below 3°C and take precautions in very hot weather to prevent rapid drying. If the trench fills with rainwater overnight, bail it out and let the bottom dry before pouring. Pouring concrete into standing water will wash out the cement and produce a weak mix at the base of the footing. Cover the top of the footings with polythene sheeting after pouring and leave for at least 24 hours before starting brickwork. In cold weather, extend this to 48 hours and use insulating material over the polythene to retain the heat of hydration.

Curing Times

Footings should be left to cure for at least 24 hours before any brickwork begins. For garden walls, 48 hours is a safer minimum, especially in cooler weather. Structural engineers typically specify 7 days before loading footings with significant weight. The concrete reaches approximately 50% of its final strength after 3 days and 65% after 7 days. For a standard garden wall, starting brickwork after 48-72 hours is common practice among builders, provided the weather has been mild. Keep the surface of the footings damp during curing by covering with polythene. In summer, this prevents the surface from drying out and forming a weak, dusty layer that reduces the bond between the footing and the mortar bed for the first course of bricks.

Estimated Cost

Prices for concrete materials in the UK vary by region and supplier. Using ready-mix bags, approximately 38 x 20kg bags may cost around £152-£228 at typical retail prices of £4-6 per bag. If you mix your own, the individual materials may cost roughly £100-£155 (cement £25-£40 for 5 x 25kg bags, sharp sand £35-£55 for 1 bulk bag, aggregate £40-£60 for 1 bulk bag). For a job this size, mixing your own concrete from bulk materials may be significantly cheaper than buying individual ready-mix bags. Consider ordering a bulk bag (dumpy bag) of sand and aggregate from a local builders’ merchant for the best price. If you need to hire a cement mixer, expect to pay £25-35 per day from most tool hire companies. A wheelbarrow, shovel, and spirit level are also essential tools you may need to buy or borrow.

Frequently Asked Questions

How much concrete do I need for 3 m footings?

For 3 m footings, you will need approximately 0.304m³ of concrete, or 0.334m³ once a 10% waste allowance is added. That works out at 38 x 20kg bags of ready-mixed concrete. If mixing your own with a C20 mix (1:2:4), you will need around 107.4kg of cement, 229.1kg of sharp sand, and 429.6kg of 20mm aggregate. The bag and material quantities include the 10% waste allowance.

How many bags of concrete for 3 m footings?

You will need 38 x 20kg bags of ready-mixed concrete for 3 m footings. This is based on a total volume of 0.334m³, which includes 10% waste. Each 20kg bag yields approximately 0.009m³ of mixed concrete. For larger projects, buying bulk materials (cement, sand, and aggregate separately) is usually more cost-effective than individual ready-mix bags.

What mix ratio should I use for footings?

For strip footings, a C20 mix (1:2:4) is a common choice for garden walls. Structural or retaining walls may need a stronger C25 mix (roughly 1:1.5:3) and an engineer's design. Always check with your local building control office if you are unsure. The concrete should be firm enough to support brickwork within 24-48 hours.

How long does concrete take to set for footings?

Strip footings set within 4-6 hours but should be left for at least 24-48 hours before starting brickwork. In cold weather, extend this to 72 hours. The concrete reaches approximately 50% of its final strength after 3 days and 65% after 7 days. Full design strength is reached at 28 days. Cover the footings with polythene after pouring to retain moisture and protect from rain.

These calculations are estimates based on standard manufacturer coverage rates. Actual quantities may vary depending on surface conditions, wastage, and application technique. Always verify quantities with your supplier before purchasing.

Related Calculators